Timeline
01.
January - March 2023
Pre-Planning Council Consultation
02.
March 2023
EIA Screening & Parish Consultation
03.
April - May 2023
Community Consultation
04.
Summer 2023
Planning application submission to Huntingdonshire District Council
05.
Winter 2023
District Council will consider and determine the application
In Progress
06.
Summer 2024
Earliest commencement of Construction (if planning permission is granted)
In Progress
Additional Information
We have submitted a full planning application to Huntingdonshire District Council (ref: 23/01507/FUL), click
here
to access the application.
1
Completed
2023-03-10
In Progress
2
Completed
2023-03-10
In Progress
3
Completed
2023-05-05
In Progress
4
Completed
2023-08-04
In Progress
5
In Progress
6
In Progress
The Project
Site Location
Timeline
Benefits
Proposed impact
FAQs
Key Project Documents
Supportive Comments
Back to home page